Rural Drinking Water Supply is a State subject. For improving the coverage of adequate & safe drinking water to the rural population, Ministry provides technical & financial assistance through a Centrally Sponsored Scheme ‘National Rural Drinking Water Programme (NRDWP)’. The Programme was launched on 01.04.2009. The Programme is being implemented in all States and two Union Territories (Andaman & Nicobar Islands and Puducherry). The Programme has been restructured in November 2017 to make it more competitive, outcome based and result oriented. The assistance is to achieve the aim to provide every rural person with adequate safe water for drinking, cooking and other domestic basic needs on a sustainable basis which is to be readily and conveniently accessible at all times and in all situations. This is in line with United Nations Sustainable Development Goal (SDG) Target # 6, i.e. ‘By 2030, achieve universal and equitable access to safe and affordable drinking water for all’.

Funding under NRDWP

a) The Earmarking of funds at the Central level is as under:

Earmarking of FundsPercentage
JE-AES affected high priority districts with bacteriological contamination2
North Eastern (NE) States10
Non-NE States / UTs88

b) Funds are set aside for two focused sub-programmes which is as under:

Rural Water Supply & Sanitation Projects for Low Income States (RWSSP-LIS) – being executed in Assam, Bihar, Jharkhand & Uttar PradeshAllocation as per the Project guidelines
National Water Quality Sub-Mission (NWQSM)Allocation as per the NWQSM guidelines

c) Component, Purpose and fund sharing pattern:

PurposeFund sharing pattern
Coverage
Normal Component (75%)
Sustainability (Functionality) component (25%).

These funds are for piped water supply schemes only.

However, 5% (max.) of every release can be used for each of following activities:
o Support
o WQM&S (Water Quality Monitoring & Surveillance)
In case, a State is unable to use the funds for Support and WQM&S activities, unused funds may be used for PWS schemes.

Sustainability (Functionality) component is released based on functionality status of completed piped water supply schemes under NRDWP as third party verification.

Part (1/3) of Normal Component is released after Pre-Financing of Central Share by the States
100:0 for UTs
90:10 for NE and Himalayan States
50:50 for other States



For Support & WQM&S
  • 100:0 for UTs
  • 90:10 for NE and Himalayan States
  • 60:40 for other States
JE-AES: To be used for PWS schemes and conversion of public shallow hand pumps to India Mark II or higher version etc.
  • 90:10 for Assam
  • 50:50 for other States

Weightage for Allocation of Funds amongst States for Coverage purpose:

CriteriaWeightage(%)
Rural Population (as per last Census)40
Rural SC and ST population (as per last Census)10
States under DDP, DPAP, HADP and special category Hill States in terms of rural areas40
Population (as per IMIS) residing in habitations having affected by chemical contaminants including heavy metals (as on 31st March of preceding financial year)10
Total100

Provision for SCs and STs

The NRDWP has special provisions to ensure coverage of the Scheduled Caste and Scheduled Tribe population with potable water supply. 22% and 10% of the funds are earmarked for the use in SC and ST dominated areas respectively. The criteria for fund allocation to States under the NRDWP, the rural SC and ST population of the State has a weightage of 10%. Thus States with higher SC and ST population get a higher allocation of NRDWP funds.

Progress of NRDWP in North Eastern States

10% of the funds are earmarked for the North Eastern States.

Mitigation of Japanese Encephalitis/Acute Encephalitis Syndrome (JE/AES)

Under National Rural Drinking Water Programme, 2% of allocation of funds is earmarked for 60 high priority Japanese Encephalitis (JE) / Acute Encephalitis Syndrome (AES) affected district identified by the Ministry of Health and Family Welfare.

Rural Water Supply and Sanitation Project- Low Income States (RWSSP-LIS)

Rural Water Supply and Sanitation Project-Low Income States (RWSSP-LIS) costing Rs. 6174 Crore is being implemented since June 2014 with the support of World Bank to improve piped water supply in Assam, Bihar, Jharkhand and Uttar Pradesh. The Project is planned to be completed by March 2020 and expected to benefit 75 lakh population and 16,933 habitations.

National Water Quality Sub-Mission (NWQSM)

National Water Quality Sub-Mission had been launched on 22nd March, 2017 to provide safe drinking water to about 28,000 arsenic / fluoride affected habitations over a span of 4 years.

SWAJAL – A Community Led Approach to Rural Piped Drinking Water Supply

Swajal, a community demand driven, decentralized, single village, preferably solar powered, mini PWS programme for aspirational districts identified by NITI Aayog has been launched. The States may use Flexi Funds of NRDWP releases.

National Centre for Drinking Water, Sanitation and Quality (NCDWS&Q)

A National Centre for Drinking Water, Sanitation and Quality (formerly known as International Centre for Drinking Water Quality) registered under Societies Registration Act. 1860 is set up at Kolkata as an autonomous Institution under the Ministry. The scope of work of the Centre was initially limited to undertake activities under drinking water quality sector. Keeping in view the challenges in sanitation sector, the scope of work of the Centre has been expanded to monitor the work relating to Swachh Bharat Mission (Gramin) since October, 2018.

NRDWP Documents


S.No Title Date Attachment
41 Letter regarding Amendment in Swajal Guidelines regarding Opening of separate Saving Bank (SB) accounts for the Implementation of Swajal Yojna in the Gram Panchayats of the aspirational districts of the State for Capital Cost and O & M cost(10.03.2019) 20/03/2019 Download (429.17 KB) pdf
42 Letter regarding Guidelines on Swajal- Amendment thereof(11.12.2018) 20/12/2018 Download (281.66 KB) pdf
43 Letter regarding Continuation of funding of Swajal Schemes taken up in States on the basis of guidelines issued by the Ministry on 7.3.2018(17.09.2018) 17/09/2018 Download (275.86 KB) pdf
44 Swajal PPT 07/09/2018 Download (2.4 MB) pdf
45 Letter regarding Implementation on Swajal schemes in aspirational district(06.09.2018) 07/09/2018 Download (491.97 KB) pdf
46 Swajal Guidelines 31/08/2018 Download (7.93 MB) pdf
47 Minutes of the review-cum-consultation meeting held on 2nd August, 2018 under the Chairpersonship of Joint Secretary (W) MDWS (21.08.2018) 21/08/2018 Download (1.16 MB) pdf
48 Constitution of the Task Force regarding SWAJAL Pilot Project(08.02.2018) 08/02/2018 Download (635.63 KB) pdf